Completed mainline construction and splicing, actively turning up customers on:
Stoney Fork Road
Lipscomb Road
Construction has started on the roads below:
Stewartville Road Primary Main Line – (from SRHS to Jordantown Road) – (aerial plant)
East Lake Church Neighborhood
Hendrick Store Road - (Bore Shots completed, beginning mainline - buried)
Timberwood Lane - (Bore Shots completed, beginning mainline - buried)
Crystal Shores Drive - (Bore Shots completed, beginning mainline - buried)
Wayfarer Lane - (Bore Shots completed, beginning mainline - buried)
Custers Cove Way - (Bore Shots completed, beginning mainline - buried)
Brook Run - (beginning Bore Work)
White Cap Lane - (beginning Bore Work)
Aspen Road - (beginning Bore Work)
Red Oak Road - (beginning Bore Work)
Peninsula Drive - (waiting on marking)
E Road, D Road, B Road - (waiting on marking)
Bent Tree Road - (waiting on marking)
Oak Hollow Road - (waiting on marking)
Pine Knob Circle - (waiting on marking)
Meadow Point Drive - (waiting on marking)
Additional Roads
Harveys Creek Road, Staunton River Court, Holy Court, Sunset Knoll Lane, Bramlett Road, Shane Road, Anna Lane have all been built and have been released to installs.
Huddleston Expanded Footprint
Permits pending submission or pending approval with VDOT
Smith Mountain Parkway
Dundee Road
Altice Road
Bold Branch
Patmos Church Road
Feldspar
October 2022 Plan
Construction for the above roads will continue with installation available shortly afterwards.
Construction scheduled to begin on Moneta Road, from Food Lion to the Hales Ford Bridge. (buried and aerial plant)
Permits expected for the roads below:
Dickerson Mill Road
Emmaus Church
Diamond Hill Road
Goodview Road (Diamond Hill Side)
Trading Post Road
*Availability and timeline is subject to change. These dates should be considered as good faith estimates.
Contact us for details.