Monthly Update - October 2022

  • Writer: Woody Watts
    Woody Watts
  • Oct 16, 2022
  • 2 min read

Current Month report

Continuing to actively turning up customers.

- Stoney Fork Road - continued

- Lipscomb Road - Continued

Main Line Construction continues.

- Stewartville Road Primary Main Line – (from SRHS to Jordontown Road) – Aerial plant – delayed due to AEP permit waiting approvals

Construction continues at the EastLake Church Neighborhood

- Hendrick Store Road - (mainline – buried construction continues)

- Timberwood Lane - (mainline – buried construction continues)

- Crystal Shores Drive - (mainline – buried construction continues)

- Wayfarer Lane - (mainline – buried construction continues)

- Custers Cove Way - (mainline – buried construction continues)

- Brook Run - (in construction schedule - continues)

- White Cap Lane - (in construction schedule - continues)

- Aspen Road - (in construction schedule - continues)

- Red Oak Rd - (in construction schedule - continues)

- Peninsula Drive - (in construction schedule - continues)

- E Road, D Road, B Road - (after further survey - changed to drops only for this campground)

- Bent Tree Road - (in construction schedule - continues)

- Oak Hollow Road - (in construction schedule - continues)

- Pine Knob Circle - (in construction schedule - continues)

- Meadow Point Drive - (in construction schedule - continues)

Huddleston Expanded Footprint

Permits pending submission or pending approval with VDOT

- Smith Mountain Parkway (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Dundee Road (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Altice Road (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Bold Branch (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Patmos Church Road (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Feldspar (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

Expanded Moneta Foot Print

Permits pending submission or pending approval with VDOT

- Construction scheduled to begin on Moneta Road (from Food Lion to the Bridge) – (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Dickerson Mill Road - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Emmaus Church - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Diamond Hill Road - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Goodview Road (Diamond Hill Side) - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Trading Post Road - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

 
 

Contact

1123 Celebration Ave

Moneta, VA 24121

contact@zitel.com

 540-328-1970 / 800-936-6082

Join our mailing list

Our team is excited to serve you and can't wait to connect you!

Thanks for submitting!

Follow us on

  • Instagram
  • Facebook

© 2024 by ZiTEL LLC. 

PRIVACY POLICY

We do not retain or sell any personal data of our customers, nor do we track or retain any history of your internet usage.

bottom of page